T1 - Best practices for implementing industrialized construction projects
T2 - lessons from nine case studies
AU - Wuni, Ibrahim Yahaya
AU - Shen, Geoffrey Qiping
AU - Darko, Amos
N1 - Funding Information:
Finally, Cases #4, #8 and #9 revealed that the shorter construction time in IC projects generates tight demand for upfront cash inflows to fabricate the modules. For instance, the manufacturer of Case #4 received an initial 80% payment to start fabrication due to the large upfront investment requirement and the retentions released when the project is completed. As such, the planning of IC projects should consider the potential tight demand for funding.
Publisher Copyright:
© 2021, Emerald Publishing Limited.
PY - 2021
Y1 - 2021
N2 - Purpose: Industrialized construction (IC) leverages manufacturing principles and innovative processes to improve the performance of construction projects. Though IC is gaining popularity in the global construction industry, studies that establish the best practices for implementing IC projects are scarce. This study aims to benchmark practical lifecycle-based best practices for implementing IC projects. Design/methodology/approach: The study used a qualitative research design where nine IC cases from Australia, Singapore and Hong Kong were analysed to identify best practices. The methodological framework of the study followed well-established case study research cycle and guidelines, including planning, data collection, data analysis and reflection on findings. Findings: The study identified and allocated key considerations, relevant stakeholders, best practices, typical deliverables and best indicators to the different construction lifecycle phases of IC projects. It also developed a lifecycle-based framework of the best practices for IC projects. Practical implications: The study provides practitioners with practical insight into how best to effectively implement, manage and evaluate the performance of the IC project lifecycle phases. The proposed framework can serve as a practical diagnostic tool that enables project partners to evaluate the performance upfront progressively and objectively in each project lifecycle phase, which may inform timely corrective actions. Originality/value: The study’s novelty lies in developing a framework that identifies and demonstrates the dynamic linkages among different sets of best practices, typical outputs and best practice indicators across the IC project lifecycle phases.
AB - Purpose: Industrialized construction (IC) leverages manufacturing principles and innovative processes to improve the performance of construction projects. Though IC is gaining popularity in the global construction industry, studies that establish the best practices for implementing IC projects are scarce. This study aims to benchmark practical lifecycle-based best practices for implementing IC projects. Design/methodology/approach: The study used a qualitative research design where nine IC cases from Australia, Singapore and Hong Kong were analysed to identify best practices. The methodological framework of the study followed well-established case study research cycle and guidelines, including planning, data collection, data analysis and reflection on findings. Findings: The study identified and allocated key considerations, relevant stakeholders, best practices, typical deliverables and best indicators to the different construction lifecycle phases of IC projects. It also developed a lifecycle-based framework of the best practices for IC projects. Practical implications: The study provides practitioners with practical insight into how best to effectively implement, manage and evaluate the performance of the IC project lifecycle phases. The proposed framework can serve as a practical diagnostic tool that enables project partners to evaluate the performance upfront progressively and objectively in each project lifecycle phase, which may inform timely corrective actions. Originality/value: The study’s novelty lies in developing a framework that identifies and demonstrates the dynamic linkages among different sets of best practices, typical outputs and best practice indicators across the IC project lifecycle phases.
KW - Best practices
KW - Case studies
KW - Framework
KW - IC projects
KW - Industrialized construction
KW - Lessons learned
UR - http://www.scopus.com/inward/record.url?scp=85112523187&partnerID=8YFLogxK
U2 - 10.1108/CI-04-2021-0070
DO - 10.1108/CI-04-2021-0070
M3 - Journal article
AN - SCOPUS:85112523187
SN - 1471-4175
JO - Construction Innovation
JF - Construction Innovation
ER -